Detroit Public Schools Community District

Board of Education · Capital Programs Update

Capital Projects Board Packet

Detroit Public Schools Community District

What’s in this packet

A plain-language summary of every active capital project in the district: the money, the timeline, who’s building, and how to get involved. Use the filters above to focus on your feeder pattern, or print/save the full packet for a community meeting.

Reporting period

August 3, 2026 (current snapshot)

Snapshot ID

S-2026-08-03

Published

August 3, 2026 — 5 hours ago

Operator

Chatoris Jones

Packet history
Current packet auto-updates with each published refresh
PacketPublishedProjectsBudgetSnapshot
Current — July 2026LiveAugust 3, 202612$173,900,000S-2026-08-03
June 2026 Board UpdateArchivedJuly 2, 202611$158,600,000S-2026-07-02
May 2026 Board UpdateArchivedJune 1, 202610$128,400,000S-2026-06-01
April 2026 Board UpdateArchivedMay 4, 20269$119,200,000S-2026-05-04

Every published packet is preserved as an immutable version tied to its data snapshot. Historical figures reflect the portfolio as it stood on each publish date.

Section 1

At A Glance

Active projects

12

Schools impacted

12

Total budget

$173,900,000

Avg. complete

47%

The district’s capital programs currently include 12 active capital projects across 12 schools, with a combined approved budget of $173,900,000. $46,800,000 (27%) has been deployed as of this reporting period. Average construction progress is 47%.

What changed since last packet: available next refresh cycle. Quarter-over-quarter comparisons (budget burn, schedule slip, deployment ratio) will appear here as soon as a second published snapshot is available for diff.

Section 2

Where The Money Is Going

Allocated is the total approved for this funding source. Deployed is what’s actually been spent so far.

SourceAllocatedDeployedDeployed %Projects
Bond Program$129,840,000$36,408,42928.0%10
Federal Grant (ESSER)$21,160,000$5,748,36727.2%4
State Capital Outlay Grant$12,700,000$2,401,09918.9%2
Local Millage$10,200,000$2,242,10522.0%2
Total$173,900,000$46,800,00012

By capital program

The same portfolio grouped by funding “bucket.” Each program can draw on more than one funding source above.

ProgramBudgetSpentProjectsShare
Facility Master Plan$83,300,000$18,450,000447.9%
Anchor Investments$60,000,000$8,700,000234.5%
Annual Board-Approved Funds$30,600,000$19,650,000617.6%

Section 3

Where Projects Are In Their Lifecycle

Every project moves through four phases on its way to opening day. Hover any phase below to see what it means.

1. Planning

1

project · 8% of total

Defining scope and budget. No design work yet.

2. Design

1

project · 8% of total

Architects drawing detailed plans and blueprints.

3. Pre-Construction

1

project · 8% of total

Permits and contractor selection. Work starts soon.

4. Construction

9

projects · 75% of total

Active build at the site.

Breakdown by feeder pattern

FeederPlanningDesignPre-ConstructionConstructionTotal
Pershing·1124
Henry Ford···33
Southeastern···22
Western1··12
Cody···11

Section 4

Wrapping Up & Coming Soon

Section 5

Projects That Need Watching

These projects are now expected to finish later than originally promised when work began. The number of days shows how far past the original completion date the project has slipped.

ProjectPhaseBudgetDays late
Pershing High SchoolSchool ReplacementDesign$45,000,000+92d
Phoenix PK-8 (New SW School)School ConstructionPlanning$38,000,000+92d
Hutchinson ElementaryInterior and SystemsConstruction$5,300,000+44d

Section 6

All Projects

12 results

IDTypePhaseView
CP-003Pershing High SchoolNew BuildDesign$45,000,000$5,500,00010%Details
CP-007Phoenix PK-8 (New SW School)New BuildPlanning$38,000,000$2,100,0005%Details
CP-005Western High SchoolAdditionConstruction$18,200,000$6,400,00040%Details
CP-002Cooley Site RedevelopmentAthleticsConstruction$15,000,000$3,200,00025%Details
CP-004Davis Aerospace HSRenovationPre-Construction$14,600,000$1,200,0008%Details
CP-001Southeastern High SchoolNew BuildConstruction$12,500,000$8,750,00070%Details
CP-006Henry Ford High SchoolRenovationConstruction$9,800,000$7,900,00085%Details
CP-008Charles Wright AcademyRenovationConstruction$6,500,000$4,100,00060%Details
CP-012Hutchinson ElementaryRenovationConstruction$5,300,000$1,900,00035%Details
CP-011Nolan ElementaryRenovationConstruction$4,800,000$2,000,00045%Details
CP-009Ann Arbor Trail ElementaryDecommissionConstruction$2,200,000$1,800,00090%Details
CP-010Greenfield Union SchoolDecommissionConstruction$2,000,000$1,950,00095%Details

Section 7

How To Participate

Next Board of Education meeting

August 17, 2026

5:30 PM7:30 PM

Fisher Building, 3011 W Grand Blvd, Detroit, MI 48202

Public comment: Sign up to speak in person at the door beginning 30 minutes before the meeting, or submit written comment by 12:00 PM the day of the meeting through the Board Office.

DPSCD Office of Capital Programs

Phone
(313) 873-7900
Office hours
Monday – Friday, 8:30 AM – 4:30 PM
Subscribe to updates

Section 8

Where This Data Came From

All figures in this packet are computed from snapshot S-2026-08-03, published August 3, 2026 (5 hours ago) by Chatoris Jones.

Source file: DPSCD_Capital_Projects_202608_v1.xlsx

This packet is auto-generated from the live portal. For verification of any individual project, see the Data Quality page or the per-project “Verify this data” details.

DPSCD Capital Programs · Board Packet · August 3, 2026S-2026-08-03
Showing snapshot S-2026-08-03 published 5 hours ago by Chatoris Jones
August 3, 2026 (2026-08-03T17:18:00.288Z)
Detroit Public Schools Community District

DPSCD Capital Projects

An interactive transparency portal for capital improvement projects delivered through the Detroit Public Schools Community District’s capital programs.

Students Rise. We All Rise.

© 2026 Detroit Public Schools Community District. Public data — free to share.About This Site