ConstructionRenovation·Pershing feeder·Annual Board-Approved Funds·CP-011

Nolan Elementary

Systems Upgrade

HVAC and electrical upgrades.

19701 Burt Rd, Detroit, MI 48219

Open on map
Nolan Elementary construction site
Nolan Elementary
Illustrative site photo. Stock imagery used for preview; replaced with project-specific photography on production launch.

Where Things Stand

HVAC and electrical systems upgrade underway. Mechanical rooms 60% complete.

Construction progress45%

Schedule

Started
April 1, 2025
Originally due
Now expected
December 15, 2025

Where the Money Comes From

  • Bond Program100% of budget
    $4,800,000

Budget Summary

Approved budget$4,800,000
Spent to date$2,000,000
Remaining$2,800,000

42% of budget used

Who Is Building It

General contractor
TBD
Architect / engineer
TBD

Where This Data Came From

Last updated August 3, 2026 (5 hours ago) by Chatoris Jones.

Verify this data
Snapshot
S-2026-08-03
Row hash (SHA-256)
3e3d3b0c3abd83204378a846c7d8be354fe8e7bf7bedfccd72f41a8b81a57aaf