ConstructionRenovation·Southeastern feeder·Annual Board-Approved Funds·CP-012

Hutchinson Elementary

Interior and Systems

Classroom upgrades and partial system replacement.

10030 E Warren Ave, Detroit, MI 48214

Open on map

Where Things Stand

Classroom upgrades and selective system replacement in progress.

Construction progress35%

Schedule

Started
April 15, 2025
Originally due
November 16, 2025
Now expected
December 30, 2025

Where the Money Comes From

  • Bond Program80% of budget
    $4,240,000
  • Federal Grant (ESSER)20% of budget
    $1,060,000

Budget Summary

Approved budget$5,300,000
Spent to date$1,900,000
Remaining$3,400,000

36% of budget used

Who Is Building It

General contractor
TBD
Architect / engineer
TBD

Where This Data Came From

Last updated August 3, 2026 (5 hours ago) by Chatoris Jones.

Verify this data
Snapshot
S-2026-08-03
Row hash (SHA-256)
941f73f2b7399e11e0f9e4517ecc5ccb17db4e7c97fc5b514a2571acf402cefd

The hash above is a unique fingerprint of this project's data. If anything changes, the fingerprint changes too. That way you can confirm the numbers you're reading are the exact ones the district published. How this works