ConstructionNew Build·Southeastern feeder·Facility Master Plan·CP-001

Southeastern High School

CTE Expansion

Construction of new CTE annex including welding and CNC labs.

3030 Fairview St, Detroit, MI 48214

Open on map

Where Things Stand

Construction is well advanced; CTE annex shell complete and welding/CNC lab fit-out underway. Project is past its original completion date and is being closely tracked for close-out.

Construction progress70%

Schedule

Started
June 15, 2024
Originally due
Now expected
September 30, 2025

Where the Money Comes From

  • Bond Program80% of budget
    $10,000,000
  • Federal Grant (ESSER)20% of budget
    $2,500,000

Budget Summary

Approved budget$12,500,000
Spent to date$8,750,000
Remaining$3,750,000

70% of budget used

Who Is Building It

General contractor
Gilbane
Architect / engineer
Quinn Evans

Where This Data Came From

Last updated August 3, 2026 (5 hours ago) by Chatoris Jones.

Verify this data
Snapshot
S-2026-08-03
Row hash (SHA-256)
b79239093b63db3c1a549b3fc85d82b5e5fc646b07c9e33d16b273b63f5548f8

The hash above is a unique fingerprint of this project's data. If anything changes, the fingerprint changes too. That way you can confirm the numbers you're reading are the exact ones the district published. How this works