ConstructionRenovation·Henry Ford feeder·Annual Board-Approved Funds·CP-008

Charles Wright Academy

Interior

Interior upgrades, classrooms, lighting.

17425 Burt Rd, Detroit, MI 48219

Open on map
Charles Wright Academy construction site
Charles Wright Academy
Illustrative site photo. Stock imagery used for preview; replaced with project-specific photography on production launch.

Where Things Stand

Interior upgrades and classroom refresh underway. LED lighting conversion 70% complete.

Construction progress60%

Schedule

Started
July 1, 2024
Originally due
Now expected
November 1, 2025

Where the Money Comes From

  • Bond Program100% of budget
    $6,500,000

Budget Summary

Approved budget$6,500,000
Spent to date$4,100,000
Remaining$2,400,000

63% of budget used

Who Is Building It

General contractor
TBD
Architect / engineer
Fanning Howey

Where This Data Came From

Last updated August 3, 2026 (5 hours ago) by Chatoris Jones.

Verify this data
Snapshot
S-2026-08-03
Row hash (SHA-256)
9505a7040b6bfda14afed5eb2028b4f67ea0ada491d5a66a18a56b2c8338e46c

The hash above is a unique fingerprint of this project's data. If anything changes, the fingerprint changes too. That way you can confirm the numbers you're reading are the exact ones the district published. How this works