Pre-ConstructionRenovation·Pershing feeder·Facility Master Plan·CP-004

Davis Aerospace HS

Adaptive Reuse

Renovation of airport terminal for aviation program.

19711 W Chicago St, Detroit, MI 48228

Open on map

Where Things Stand

Adaptive reuse design complete. Pre-construction mobilization and abatement scope being finalized.

Construction progress8%

Schedule

Started
August 15, 2025
Originally due
Now expected
September 1, 2026

Where the Money Comes From

  • Federal Grant (ESSER)100% of budget
    $14,600,000

Budget Summary

Approved budget$14,600,000
Spent to date$1,200,000
Remaining$13,400,000

8% of budget used

Who Is Building It

General contractor
Gilbane
Architect / engineer
Quinn Evans

Where This Data Came From

Last updated August 3, 2026 (5 hours ago) by Chatoris Jones.

Verify this data
Snapshot
S-2026-08-03
Row hash (SHA-256)
60253662f46790e7fe22aa06235889ed2d3973ece686d9552ffd6c404e6246f5

The hash above is a unique fingerprint of this project's data. If anything changes, the fingerprint changes too. That way you can confirm the numbers you're reading are the exact ones the district published. How this works